How Long does the Elizabeth plant take to manufacture a single VF from start to finish?

VL Executive

VY SS Ute - Just got 1!
Joined
Mar 3, 2004
Messages
199
Reaction score
48
Points
28
Age
41
Location
Near Bundaberg, QLD
Members Ride
3 VL's, VK EFi, VX S, VY SS Ute, VF SSVR Ute
Hi all, With the start of my Ute build getting closer (5th July) Was just wondering approximately how long it takes for a VF Commodore to be made. From the very beginning, to the very end. And driven off line and out of the factory.
 

Smashfist

Well-Known Member
Joined
Jul 25, 2014
Messages
841
Reaction score
263
Points
63
Age
44
Location
SE QLD
Members Ride
440rwhp Cammed VF Ute
A few of my shop guys just did a factory tour, suggested by staff there approx. 6 hours of labour stamped from sheet steel to driving off the line.
 

Smitty

Moderator
Joined
Oct 21, 2003
Messages
2,457
Reaction score
1,663
Points
113
Location
Bayside Melbourne
Members Ride
GenF SV340 R8 Tourer, VK race car, ZX12R
A few of my shop guys just did a factory tour, suggested by staff there approx. 6 hours of labour stamped from sheet steel to driving off the line.
... doubtful 6 hours
the paint process alone takes around 2 1/2 hrs by itself (from body proofing thru actual painting, drying and then inspection)

the original VB Commodore used to spend 37-40 hours 'on line' .. from assembly of the panels into a jig for welding
thru to driving it out into the paddock for storage . The base 6 cyclinder L model obviously taking less time than the SL/E
 

W375 redline

Active Member
Joined
Sep 17, 2016
Messages
122
Reaction score
30
Points
28
Location
Adelaide
Members Ride
W375 s2 redline
Hi there : smitty is right with the duration of the painting process : its at least 3 hours and i should know as i work in the paint plant : from start to finish is at least 2 to 3 days n thats as long as everything runs smoothly : hope this answers your question ☺
 

Brisbarnz

Active Member
Joined
Feb 3, 2014
Messages
520
Reaction score
38
Points
28
Location
Brisbane
Members Ride
Vh sle
There's a vid on utube (VE). From sheet steel to delivery. Will have all the info required
 

VL Executive

VY SS Ute - Just got 1!
Joined
Mar 3, 2004
Messages
199
Reaction score
48
Points
28
Age
41
Location
Near Bundaberg, QLD
Members Ride
3 VL's, VK EFi, VX S, VY SS Ute, VF SSVR Ute
Thanks fellas, Thought it would be around 3 or more days
 